Molloy Environmental Systems have developed a Plug and Play wastewater treatment plant using PFBR technology. The first application of this technology is a 500 PE equivalent (225litres/person/day) wastewater treatment plant at Shannonbridge, County Offaly.

The use of a plug and play containerised system suited this site due to the risk of flooding. The existing Imhoff tank was utilised as a primary settlement tank, precast concrete tanks were installed for balancing and a concrete base was constructed for the Plug and Play PFBR unit. A precast concrete screen chamber was installed for preliminary screening.